By Ihechinyere Chigemeri-Uwom
The Minister of Works, Sen. Dave Umahi, has directed Arab Contractors handling the rehabilitation of the Enugu-Port Harcourt Expressway to complete the remaining 4.5-kilometres Abia section before the end of November.
Umahi gave the directive on Friday in Aba after inspecting the progress of work on the project.
He expressed dissatisfaction with the slow pace of work on the section, warning that the contract would be revoked, if the deadline was not met.
โI am not happy with the progress of work on this 4.5-km out of the 112-km of the road.
โI am giving you a charge today. By the end of November, the entire laterite, sharp sand, and concrete work must be finished on this road.
โIf it is not done, I will revoke the contract,โ Umahi said.
He assured the contractor of prompt payment, describing the President Bola Tinubu-led administration as โa reliable partner that does not renege on its financial obligations.
โThe president is not the type that will ask you to work and he will not pay you.
โYou will be paid, because if we have paid you for the other sections, we will pay for this one too,โ he said.
Umahi praised Gov. Alex Otti of Abia for his unwavering commitment to the development of the state andย for supporting the presidentโs infrastructure agenda.
โGovernor, I thank you, especially your push for the development of Abia is unparalleled.
โThe president has shown very serious attention to the affairs of the South-East, and road infrastructure is one of such,โ he said.
He also commended the contractors for their integrity and quality of work, recalling how the companyโs management had previously prioritised completing existing projects over taking new ones.
Umahi further directed the Federal Ministry of Workโs Controller in Abia to ensure strict supervision, vowing to return to the site weekly to monitor progress.
โI will come back every week to look at it.
โFinish the sharp sand filling, finish the concrete work, let us be left with stone base and the binders,โ he charged the company.
In his remark, Otti affirmed his administrationโs commitment to supporting federal projects for the benefit of the people of Abia.
He also pledged his administrationโs full support to ensure the timely completion of the Aba segment of the Enugu-Port Harcourt Road.
He expressed satisfaction with the progress of work, saying that with only 4.5- km remaining on the project, the end was in sight.
He said that he had secured a commitment for the project to be commissioned by December.
โWhatever it takes, like the Honourable Minister said, Iโm going to be coming here from time to time.
โI live here with you and if you need anything, please let me know,โ Otti said.
He commended the contractors for the quality of work done so far and hinted at the possibility of more projects for the company upon the successful completion of the current one.
Also, the Zonal Manager of Arab Contractors, Mr Mohammed Elian, disclosed that only five per cent of work was left on the project, expressing commitment to its completion by December.
Elian commended Abia Government for the improved security situation in the state and lauded the minister for his efforts towards the projectโs completion.
He said that the projectโs scope covered the road from Umuahia Tower to Aba Township and that the bulk of the work, particularly the dualisation, had been completed.
โWhat remains in the project is just 4.5-kilometres on one side, which is like five per cent of the entire project,โ he said.
He said that his company had received directives from its management to deploy its โfull forceโ to ensure timely delivery.
He acknowledged the promise of continued funding from the Federal Government which, he said, was crucial for completing the remaining work.
โBy Godโs grace (Inshallah), we will do our best to complete the project by December,โ Elian said.
Earlier, the Controller, Federal Ministry of Works in Abia, Mr Chidi Uwaeziozi, said that the Port Harcourt-bound lane of the road had reached an advanced stage of completion.
He also said that the entire Enugu-bound lane of the road had been fully completed.
โOn the right-hand side, which is the Port Harcourt-bound lane, it is only remaining 4.5-km, covering both the main carriageway and the service lane,โ Uwaeziozi said.
He expressed strong optimism over the timely completion of the project ahead of the December date for its inauguration. (NAN)(www.nannews.ng)
Edited by Sam Oditah