The Transmission Company of Nigeria (TCN) says it has energised two newly installed power transformers at its 330/132/33 Kilo Volt (KV) Birnin Kebbi Transmission Substation in Kebbi.
TCN made this known in a statement on its website in Abuja on Sunday by Mrs Ndidi Mbah, itโ€™s General Manager Public Affairs.
Mbah said that the 100 and 150 Mega Volt Ampere (MVA) transformers were energised at 1:18 p.m. and 2:56 p.m, on Friday.
According to her, the additional transformers have increased the substationโ€™s capacity from 300MVA to 450MVA.
โ€œAs a result of the newly installed transformers, Kaduna Electricity Distribution Company now has an additional 120 Megawatts (MW) of bulk power for distribution to customers across Kebbi, Sokoto, and environs.
โ€œThis also enables TCN to ensure normal bulk power supply to Niamey, the Niger Republic.
โ€œWe are committed to the continued expansion and maintenance of the nationโ€™s transmission system to ensure a more effective and efficient bulk power transmission nationwide,โ€ she said. (NAN)(www.nannews.ng)
Edited by Shuaib Sadiq/Muhammad Lawal
follow and like on:
X (Twitter)
Visit Us
Follow Me
YouTube
Instagram
Telegram
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments